Where we jumped in

We helped manage this project from the detailed design phase through to completion, with all defects resolved.

Challenges

This project was a real challenge as COVID caused delays in the supply chain. But through teamwork we were able to complete the project in 2021 as planned.

Added Value

By working closely with the general contractor and the client, we were able to avoid VOB letters for delays and additional costs, despite the logistical challenges caused by COVID.

Client: Shurgard

Type: Self-Storage

Started: November 2020

Completed: November 2021

Project Type: New Build

Role: Project Management

Mastered Challenges

  • COVID
  • Contaminated soil
  • Demolition

Other Projects

INDUSTRIAL

Laim

For Shurgard Self-Storage

INDUSTRIAL

Berlin

For Shurgard Self Storage

RESIDENTIAL

Munich

For Ten Brinke Group

Contact us to find out more

Jan Bak

Founder & Managing Director

e: info@bakmanagement.com
t: +49 (0)30 3989 3119

Have a project in mind?

Contact us to see if we could be a good fit. 

info@bakmanagement.com
Koppenstraße 93, 10243 Berlin
+49 (0)30 3989 3119